Notification of the construction, significant modification, or measures resulting in a change in the hazard level of AwSV facilities (excluding heating oil-fired systems and JGS facilities) Acceptance
This text comes from the German government’s official process catalogue (FIM). The rules of your state or city can differ. Always confirm with the responsible office.
In short
If you intend to construct or make significant changes to a facility that handles substances hazardous to water, or if you intend to take measures that result in a change in the hazard level, you must report this.
What it is
You must submit your notification regarding the construction, substantial modification, or change in the hazard level of a facility subject to inspection to the competent authority in a timely manner in advance.
You are not required to file a notice for the construction of these facilities if
• an application for a suitability determination under the Water Resources Act has been filed for facilities used to store, fill, or handle substances hazardous to water, or
• the facilities are subject to an approval procedure under other legal provisions, provided that compliance with the requirements of this regulation is also ensured in the approval procedure. In this case, substantial modifications to the facility that require approval are also exempt from the notification requirement.
Who can apply
The facilities must comply with the requirements of the Ordinance on Facilities for Handling Substances Hazardous to Water (AwSV). This must be demonstrated through the documentation to be submitted.
Documents you need
• Completed notification form
• Detailed documentation describing the project (site plan, drawings, supporting documents, descriptions)
• Expert opinions, if applicable
How it works
If you want to file the report online:
• Submit the application via the online service.
• The water authority will review your documents for completeness and, if necessary, request any missing information or documents.
• In addition, the substantive requirements will be reviewed, which may also result in requests for additional information.
• The authority may provisionally or permanently prohibit the project or issue a decision with conditions.
If you wish to submit the notification by mail or email:
• Fill out the forms required for the notification and send them to the lower-level water authority.
• The remaining steps in the process are the same as for the online procedure.
Deadlines
Please submit your notice to the appropriate authority at least six weeks in advance.
Last updated: 2026-11-10