In short

You do not need planning permission for certain building projects. Instead of a building permit, only a notification is required. You need an exemption from approval for this

What it is

For certain construction projects (see requirements), you do not need a building permit in Thuringia. In these cases, you must file a notice of your construction project by submitting the required documents (construction documents). Since you are not applying for a building permit with this notice, no building permit will be issued.

The documents must be submitted digitally via the online form provided for this purpose or in paper form directly to the municipality.

In general, you may begin construction one month after the municipality receives the required documents. This applies only if the municipality does not declare within this period that a simplified building permit procedure is to be conducted and does not apply for a preliminary prohibition.

If the municipality informs you before the one-month period expires that no permit process will be conducted and that the municipality is not requesting a prohibition, you may begin construction earlier.

Even if a building permit is not required, you must comply with all public law requirements. The responsibility for this lies with the building owner.

Who can apply

Exemption from the permit requirement applies only if the conditions of the Thuringian Building Code are met. In particular, the construction project must

• be one of the projects specified by law,

• not conflict with the provisions of a zoning plan, and

• utility connections must be secured.

Documents you need

In addition to the application form, all documents required for the evaluation of the project must be submitted:

• Construction drawings

• Building specifications

• Site plan

• Excerpt from the cadastral map

• Structural engineering documentation

• Parking Space Verification

• Statistical Survey Form

• Application for a Waiver or Exemption

How it works

• The building owner must submit the required documents digitally via the online form application to the building inspectorate or in paper form to the municipality.

• The municipality shall immediately forward a copy of the documents to the lower-level building authority, unless it is itself the building authority.

• The municipality may declare that the requirements for exemption from approval should be reviewed in a simplified building permit procedure or that other grounds exist for conducting the simplified approval procedure.

Fees

Depending on the chargeable building value in accordance with the administrative cost schedule of the Building Fees Ordinance.

Responsible office

Please contact the local building authority.

Good to know

The exemption from approval does not release you from the requirements to prepare and check the structural engineering certificates.

If you disagree

Objection, complaint

Legal basis

§ 62 of the Thuringian Building Code (ThürBO)
§ 64 Thuringian Building Code (ThürBO)
Sections 1 and 2 of the Thuringian Building Documentation Ordinance (ThürBauVorlVO)

Official source