Show start of construction for a project that requires planning permission or does not require planning permission

This text comes from the German government’s official process catalogue (FIM). The rules of your state or city can differ. Always confirm with the responsible office.

In short

Notify the lower building supervisory authority at least one week in advance of the start or resumption of construction projects that require approval or do not require approval.

What it is

As a building owner, you must inform the lower building supervisory authority in text form at least one week in advance of when you wish to start your building project that requires approval or does not require approval.

The same applies if you resume construction after an interruption of more than three months.

If your building project is exempt from procedures, i.e. does not require a building permit or exemption from approval, this notification is not necessary.

Who can apply

You may only start work on your construction project that requires approval or is exempt from approval once you have received the (partial) building permit or an exemption from approval.

You must submit the required structural engineering evidence at the latest with the notification of the start of construction.

Documents you need

• notification

• If necessary, the structural engineering verifications

How it works

Notify the building supervisory authority of the planned start of construction or the resumption of construction work after an interruption of more than 3 months at least 1 week in advance in text form.

The lower building supervisory authority will then check whether the conditions for starting the construction project are met. Feedback from the authority is not necessary.

Fees

• none

Deadlines

• Notification period: at least one week before the planned start of construction or resumption of construction work

Where to go

Lower building supervisory authorities

Notes

If the notification of the start of construction is not submitted or not submitted on time, this may be punished as an administrative offense.

Legal basis

§ 72 Mecklenburg-Western Pomerania State Building Code (LBauO M-V)