In short
A change of use is a change to the approved type of use of a building. When registering a business, for example, it is advisable to obtain information from the building supervisory authority in advance.
What it is
A change of use is a change to the approved type of use of a building. In most cases, the change of use - even without structural changes - requires planning permission. The change of use application is examined either in the permit exemption procedure, in the simplified building permit procedure or in the full procedure.
When registering a business, for example, it is advisable to find out in advance from the building supervisory authority whether the desired use of a building/room constitutes a change of use requiring approval.
Documents you need
•
Application form on official form with all necessary signatures
•
Building description on official form
•
site plan
•
construction drawings
•
Proof of parking space
•
Immission control report (may be required for commercial changes of use)
• Calculation of production costs and built-up areas (may be required)
Responsible office
Contact the Lower Building Supervisory Authority.
Legal basis
Thuringian Building Code