Apply for a preliminary decision
This text comes from the German government’s official process catalogue (FIM). The rules of your state or city can differ. Always confirm with the responsible office.
In short
Would you like to know whether your project is permitted and have not yet submitted a building application? Then you can submit a preliminary building application.
What it is
If you have individual legal questions about the permissibility of your building project and have not yet submitted a building application, you can submit a preliminary building inquiry.
This is useful, for example, if it is unclear whether you are allowed to realize your building project on the planned plot.
In the preliminary building application, you formulate your question so clearly that a clear answer is possible.
You will then receive a preliminary building permit for your question.
Who can apply
The application for a preliminary decision must be submitted in writing or digitally using the officially prescribed form.
Documents you need
Application for preliminary decision (digital or written)
If also required for assessment:
• Extract from the official real estate map (not significantly older than 3 months)
• site plan
• construction drawings
• Building description
• Proof of stability
• Fire protection concept
• Information on the secured development
Please contact your local building supervisory authority to find out which documents you need to submit for a decision on your specific questions.
How it works
Submit your application for a preliminary decision (digitally or in writing) to your local building supervisory authority.
The lower building supervisory authority will review your application and involve the municipality and necessary authorities.
You will then receive the preliminary decision and a notification of fees. Pay the fees
Fees
The amount of the fee depends on the scope of the inspection work.
Up to half of the fee for the preliminary decision is to be offset against the building permit fee, provided that the minimum fee for the building permit is not undercut.
Deadlines
Once you have received the preliminary decision, you can start building with a valid building permit within 3 years.
You can apply for an extension of the preliminary decision by up to 1 year.
Responsible office
The lower building supervisory authorities of the state of Saxony-Anhalt are responsible. These are the districts, independent towns and the towns belonging to the districts of Stendal, Köthen, Naumburg, Zeitz and Weißenfels.
If you disagree
You can lodge an objection.
Legal basis
Building Code (BauGB)
Land Use Ordinance (BauNVO)
§ Section 74 Building Regulations of the State of Saxony-Anhalt (BauO LSA)
Ordinance on building documents and notifications to building authorities (Bauvorlagenverordnung BauVorlVO)
Administrative regulation for technical building regulations (VV TB 2022)
Building Fees Ordinance (BauGVO)