Do you want to operate an X-ray system in technical radiography for coarse structure analysis in materials testing or make changes to the operation? Then you must notify the competent authority for radiation protection and apply for a permit.

What it is

In order to be able to operate an X-ray system in technical radiography for coarse structure analysis, you must notify the competent authority for radiation protection and apply for a permit.

You must also inform the authority if you wish to make significant changes to an existing and approved X-ray system. In this case, you will need a new permit.

Who can apply

• There are no concerns about the reliability of the applicant or the radiation protection officer.

• The radiation protection officer must have the necessary expertise in radiation protection.

• You need a sufficient number of radiation protection officers and they must have the necessary authorizations for their tasks.

• You need sufficient personnel to carry out the work safely.

• They must have sufficient equipment and take appropriate measures to comply with state-of-the-art protection regulations.

• This is a justified type of activity and does not conflict with any other public law regulations.

Documents you need

•
Main application for approval

• the operation of an X-ray facility or

• the modification of an X-ray facility

• Documents required to check the licensing requirements, e.g. plans, drawings or descriptions

• Information on the number of radiation protection officers and their authorizations

• Information on the equipment and measures taken to comply with the protection regulations

• information on the reliability and radiation protection expertise of the radiation protection officer and the radiation protection officers

• radiation protection instructions, if required

Deadlines

You must apply for approval before you put the X-ray equipment into operation. You may only put the X-ray equipment into operation once you have received written approval.

Good to know

There are no indications or special features.

If you disagree

Action before the administrative court

Official source

Last updated: 2025-12-01